Telling neighbours before disruptive work starts

By Review.LivePublished 3 min readHow we write

The piling schedule arrives: 46 driven steel piles over nine working days, starting in three weeks. Across the lane are 28 houses and a small apartment building. On your last job, the street's first warning was the hammer.

A blank freestanding notice board stands beside a paved pedestrian path and planted beds.
Photo: Kate Trysh on Unsplash

Tell them in writing before the work starts, early enough to plan around it: what will happen, the dates and hours, what they will notice, what you are doing about it, and a person who answers the phone. Deliver it to everyone who will hear, feel or be blocked by the work, and keep to what you wrote. Surprise, more than noise, is what sends people to the city. Complaints that come anyway are covered in a neighbour's complaint.

The rules are municipal, so check yours before you set dates. Vancouver, for example, requires a letter for work under a noise by-law exception permit, issued only after the permit is granted and delivered to every residence within a one-block radius 48 hours before the exempt work begins, with the time, date, location and type of work and a contact name and number. Portland, Oregon, allows pile driving from 8:00 to 18:00 on weekdays, with at least 30 days' notice to residents within about 150 m (500 ft); federal holidays are excluded.

  1. List who will notice: homes and businesses within earshot and vibration range, along the truck route, and anyone whose parking or driveway you block; the wider map is in stakeholders beyond the owner.
  2. Write one page in plain words: what, where, the dates and hours, what they will notice, what you are doing about it, and when it ends.
  3. Name a person and a phone answered during working hours, briefed on what they may promise. An office line that goes to voicemail sends people to the city.
  4. Deliver it door to door, after any required permit approval, by the local deadline and earlier where allowed; post it on the hoarding and in apartment lobbies.
  5. Remind and update: a card two days before, a new notice when dates change, and a last one when the work ends.

Common mistakes

  • Writing in contract language: "pile installation operations" instead of "loud banging".
  • Delivering it the day before, or only taping it to the fence.
  • Promising quiet hours the crews then break.
  • No second notice when the dates slip.

Checklist

Before the notice goes out

  • Local hours and notice rules checked
  • Everyone affected listed, truck route included
  • Dates, hours and end date
  • What they will notice, in plain words
  • What you are doing about it
  • A named person who answers
  • Reminder and update dates set

Check your understanding

Piling slips a week after the notice has gone out. What do you do, and why?

Show the answer
Send a new notice with the new dates at once, and call back anyone who asked about the first. People who planned their week around your dates will read silence as a broken promise, and your next notice will carry less weight.