BC cranes and hoists: receive the equipment, personnel and lift records
A manager hires a mobile crane for a weekend operation. The supplier’s folder contains equipment and operator records that do not all identify the proposed arrangement.

A crane booking reserves a resource; it does not establish readiness for the planned operation. Part 14 has requirements that differ by equipment and activity. Start with the actual machine and proposed work, then identify the applicable equipment records, personnel qualifications, inspection and lift-planning requirements. A tidy folder labelled “crane certificate” cannot show which machine, person or configuration its contents cover.
Receive the evidence for the proposed operation
- Identify the equipment and work first. Record the supplier, machine identity and type, proposed load and location, and the configuration information received. Ask the responsible qualified personnel to identify the applicable provisions and operating instructions. Do not apply a mobile-crane record requirement to every hoist by default. Keep the planning record connected to the actual operation instead of using a previous project’s machine name as a placeholder.
- Match the equipment documents to that identity. Receive the applicable certification, inspection, maintenance and manufacturer information through the supplier’s responsible contact. Check what each document identifies, covers and dates; send technical gaps to the appropriate qualified reviewer. Part 14 addresses changes affecting capacity or safe operation. An earlier certificate should not be treated as covering an unexplained modification, repair or different configuration without the required review.
- Separate the personnel and operating checks. Verify the applicable operator requirements and receive the arrangements for qualified rigging, signalling and supervision. Keep a person’s record separate from the equipment’s record. The Regulation includes shift checks and reporting of defects; record the actual responsible route and unresolved findings. A supplied name or a completed booking is not evidence that these checks were performed for this shift.
- Receive the required lift plan and briefing. Have the responsible team establish whether the operation meets the current critical-lift definition and other applicable planning requirements. A critical lift requires a written plan available during the lift and a documented immediate pre-job meeting, repeated for changes in people or equipment. Receive the actual plan and communication arrangements. This record does not calculate capacity, select a crane or instruct a lifting technique.
Common mistakes
- Using one generic certificate checklist for every crane and hoist.
- Confusing an operator record with equipment certification.
- Keeping a plan unchanged after its people or equipment change.
Checklist
Check five connections in the crane file
- Actual equipment and configuration.
- Applicable certification, instructions and maintenance evidence.
- Personnel qualifications and responsible communication route.
- Current inspection findings and unresolved issues.
- Required plan, briefing and reviewed changes.
Check your understanding
The crane is booked and a certificate is attached. Does that establish readiness for the lift?