Structural erection in BC: match instructions to the system and stage
A regional airport hangar receives its first structural delivery. The erector’s procedure is one paragraph, and the superintendent cannot connect it to the numbered components or the planned stages. The truss package contains design drawings but no clearly identified erection instructions.

For premanufactured open-web joists and trusses, G20.72 requires available written erection instructions from the manufacturer or a professional engineer, including temporary bracing. Start by identifying the system and the stage. Steel framing, trusses, precast and tilt-up work raise different questions; obtain the applicable requirements and responsible technical response rather than applying one paragraph to every system.
Check the requirement against the actual work
- Identify the components and the proposed stage. List the package, drawing revision and work area being released. Ask the erector to describe what will be installed and what remains incomplete afterwards. Give that information to the responsible technical reviewer. Avoid a readiness entry simply labelled “structure”; it conceals which components and conditions the received information actually addresses.
- Separate design drawings from erection instructions. Locate the instructions for the actual system and check who issued them. Identify where temporary support is addressed instead of assuming that permanent bracing details answer the question. Ask the responsible reviewer about any gap or conflicting note. A document list is useful only when the listed information covers the work being planned.
- Connect the instructions to other site activities. Bring the erector, lifting coordinator and affected trade supervisors into the review. Identify access, adjacent work and the area occupied during each stage. Obtain their applicable arrangements through the responsible processes. Do not write a lifting sequence, select bracing members or decide fall protection from a general article or a sketch in the coordination minutes.
- Track departures before they become field assumptions. Record a changed component, delivery order or proposed sequence against the affected instruction. Send the actual change to its responsible reviewer and retain the received response. Name who communicates it to the erection crew. A verbal suggestion to “make it work” leaves the next shift unable to tell whether the change was assessed.
- Release a defined stage with its conditions visible. Keep the accepted documents, pending questions and responsible contacts in the same stage record. Brief the people affected by the current arrangement and record what remains restricted. Review the next stage separately when its conditions differ. Closing an administrative item does not certify the structure or authorize removal of a temporary support.
Common mistakes
- Using a building permit drawing as the entire erection package.
- Applying truss instructions to every structural system.
- Recording a sequence change without its technical response.
Checklist
Check each erection stage
- System, components and stage identified.
- Applicable instructions and issuer located.
- Temporary support questions resolved through the proper reviewer.
- Adjacent work and separate arrangements coordinated.
- Changes and remaining restrictions communicated.
Check your understanding
The shipment includes detailed component drawings. Does that close the erection-instructions item?



