Equipment and pedestrians: receive usable separation and current movement instructions
Workers cross the parkade haul route to reach the lunch area while trucks are moving. A warning on the noticeboard has not provided a usable pedestrian arrangement. The superintendent needs a current assessed route and implemented controls, rather than rely on drivers seeing everyone in a vest.

Separate the movement problem from personal visibility alone. CCOHS's heavy-equipment guidance describes traffic planning, updated routes, trained communication and avoiding blind spots or unpermitted approaches. Apply the actual machine, task and local requirements. A high-visibility vest or apparent eye contact does not establish received permission, stopped movement or protection from another machine. This lesson supplies no exclusion distance, traffic geometry or generic spotter requirement for every operation.
Make the walking route an actual controlled arrangement
- Map the movements people really need. Identify current equipment routes, tasks, walking destinations and interfaces, including deliveries and changing work areas. Use worker and operator input through the appropriate safety process. A proposed walkway nobody can reach without crossing an unresolved route is incomplete. Do not send a person into operating blind spots to demonstrate the problem.
- Receive suitable separation and crossings. Have competent personnel assess the actual arrangement and necessary controls, favouring elimination of the conflict where feasible. Implement the received barriers, routes, crossings or operating restrictions under the applicable plan. Do not select a barrier by colour or assume cones provide impact protection. A lunch-area move also needs its actual access, facilities and project requirements reviewed.
- Give operators and walkers the current instructions. Receive trained authorized communication and any required signalling roles for the actual movements. Explain where workers may go and how an approach or crossing is authorized. Confirm affected crews and arriving drivers receive the change. Do not approach a machine because its operator glanced toward you; use the actual permitted movement and communication process.
- Check use and return changed conditions. Verify that the received route and protections are usable and maintained, with concerns reaching the responsible lead promptly. Return shifted barriers, stored material, changed equipment paths or failed communication before affected exposure. A spotter is an assessed role requiring appropriate competence; that person's presence cannot correct every visibility, support or conflicting-movement problem.
Common mistakes
- Using a vest or glance as permission to approach equipment.
- Posting a walkway plan before its controls exist.
- Forcing pedestrians into traffic when storage blocks the route.
- Assuming any spotter can resolve every movement conflict.
Checklist
The current movement arrangement retains
- Actual equipment movements and walking destinations.
- Competent separation/crossing decisions and implemented controls.
- Trained communication and clear permitted approaches.
- Instructions reaching crews, operators and arrivals.
- Usable maintained routes and immediate change response.
Check your understanding
The marked walkway is blocked, but workers can wear vests and walk behind the trucks. Is that an acceptable substitute?