Writing a schedule narrative the owner will read

By Review.LivePublished 3 min readHow we write

On the 5th, your update goes to the owner as a 460-activity PDF and a one-line email: "Updated schedule attached; completion unchanged." Three weeks later the owner's project manager asks why nobody told her that the elevator now drives the finish, and that it is waiting on her. It was on page 9.

A hand writes on paper at a wooden table beside a notebook and cup.
Photo: Unseen Studio on Unsplash

Write down what the update shows, in the order the owner needs it: the forecast finish, the critical path and how it moved, delays and their causes, the changes you made to the schedule, and what you need from others, with dates. A schedule shows dates, not reasons, and a finish date can hold while the path moves onto the owner's own decisions. Describe that path by the work it carries, so a reader who has never opened your scheduling software can understand which answer you need and what a late answer would hold up.

In this order

  1. Status: the data date, the forecast finish against the contract date and last month's forecast, in working days, and the critical path's float.
  2. The critical path in words: the chain from today to the finish, by activity name, what it ran through last month, and anything newly critical.
  3. Progress: the few activities that mattered, planned against done, and the next period's main work.
  4. Delays: the cause, the effect on the finish and the date of any notice. Report every delay; the notice itself goes separately, as notice of change explains.
  5. Changes to the schedule: activities added or deleted, logic or durations changed. The US General Services Administration's schedule clause requires a written narrative for each revision: its substance, rationale and effect on the projected substantial completion date and the available float.
  6. Needed from others: owner decisions, consultant reviews and the owner's contractors, each with a date and the days a late answer costs.

Common mistakes

  • "See attached" as the narrative.
  • Walking through every activity, so the change that matters is lost.
  • Leaving out the shortened duration that holds the finish.
  • Blame instead of facts and dates.

Checklist

Before you send it

  • Finish against the contract date and last month
  • Critical path in words, with what changed
  • Every delay: cause, effect, notice date
  • Every change to logic or durations, with its reason
  • Decisions needed, with dates and the cost of lateness
  • One page

Check your understanding

The finish holds only because you shortened three critical drywall activities, one after another, by two working days each. What does the narrative say?

Show the answer
It lists the three cuts, the reason for each, such as a second crew the trade has confirmed, and their effect: without them the finish moves six working days. An unexplained cut, found later, costs the owner's trust in every update.

Sources

  1. GSAM 552.236-15 Schedules for Construction Contracts, paragraph (h) Revisions to the scheduleU.S. General Services Administration (Acquisition.gov) · United States General Services Administration construction contracts · accessed
  • Marked drawings, pencils and a green drawing triangle lie beside a keyboard on an office desk.

    Scheduling

    Showing how a change moved the finish date

    Prepare a simple time impact analysis: add a change's activities to the last accepted update, recalculate, and show the owner how the finish date moved.

    3 min read

  • A hand links printed sheets pinned to a wall with string, tracing a chain of connected steps.

    Scheduling

    The critical path in plain language

    Find the chain of activities that sets your finish date, confirm it with float, and explain to crews why a slip on that chain moves the whole job.

    3 min read

  • A multi-storey concrete frame under construction, with steel-stud exterior walls going in and shoring still in place, under a blue sky.

    Project management

    The one-page weekly report to the owner

    Write a one-page weekly report that tells the owner where the job stands: progress, the next two weeks, risks, decisions needed from them and changes.

    3 min read