Updating the schedule every week in thirty minutes
Friday, 15:30, in the site trailer. The schedule still shows the level 4 deck pour finishing on Monday; it happened yesterday. The last update was five weeks ago, the owner's meeting is first thing next week, and nobody can say whether the finish date has moved.

A schedule stops being a forecast once its dates fall behind the site. Updating means recording what actually happened up to a cut-off, the data date, and letting the logic recalculate everything after it; actual progress plus logic is what gives a realistic forecast. Your contract may require a formal update at a set interval; a 2024 review of eleven US state transportation specifications found updates mostly due monthly. A short weekly update keeps the formal one easy and catches slips while they are small.
The thirty-minute routine
- Fix the data date, for example Friday at the end of shift. Nothing after it goes in as actual.
- Enter actual starts and finishes from the daily reports, not from memory.
- Ask each foreman for remaining working days on work in progress, rather than a percentage. A percentage can sit at 90 for weeks.
- Correct the logic where work went out of sequence, such as a crew that started before its predecessor finished, and note why.
- Read what moved: the forecast finish, the critical path, and every chain whose float fell since last week.
- Write three lines — what moved, why, and what you will do — and file them with the update. They become next month's narrative.
Common mistakes
- Updating percentages but not remaining durations, so the forecast stays optimistic.
- Overwriting the baseline, so nothing is left to compare against.
- Changing logic quietly to keep the finish date looking good.
- Updating in the office without a word from the site.
Checklist
The Friday update
- Data date set
- Actual dates entered from the daily reports
- Remaining days from each foreman
- Out-of-sequence work corrected and explained
- Forecast finish compared with last week
- Critical path and falling float checked
- Three lines written and filed
Check your understanding
Three critical activities finished late this week, yet the updated schedule shows the same finish date. What do you check first?