Planning for winter work
The September schedule update puts the level 1 slab pour in mid-December and exterior framing into January. The estimate carries a single round number for winter conditions. The project manager asks the superintendent what that number is supposed to buy.

Winter adds cost and time an estimate rarely shows: enclosures, fuel, heater tending, snow clearing, short days, slower crews, and materials that cannot go in below their minimum temperature. It is also regulated work, and the rules differ: the Canadian Centre for Occupational Health and Safety notes that some Canadian jurisdictions set acceptable temperature ranges while others use published cold-stress limits.
- List the temperature-sensitive work, such as concrete, masonry, roofing, sealants and coatings, with minimum conditions from the specification and product data.
- Decide enclosure and heat for each activity: who supplies and tends it, at what cost, and what the Division 01 sections on temporary utilities and enclosures say. In British Columbia, bracing for a scaffold enclosed by tarps or another cover must follow a professional engineer's instructions.
- Treat heaters as a hazard: fuel-fired heaters give off carbon monoxide. Ontario's construction health and safety association advises indirect-fired heaters for enclosed spaces and testing heated areas for carbon monoxide, and says only workers holding a record of training may operate propane, gas or oil heaters there. US federal rules add requirements for fresh air and for clearance from combustible tarps.
- Agree cold-weather concreting before the first cold pour: the specification, the concrete standard it cites and the engineer set protection, temperatures, curing and stripping times. US ready-mix industry guidance says fresh concrete should be protected from freezing, with protection ready before placement and fuel-fired heaters in enclosed spaces vented, for safety and to protect the fresh surface. Add these to the pre-pour check.
- Plan crew welfare to your jurisdiction's cold-stress rules. Where workers may be exposed to cold stress, British Columbia requires a cold stress assessment, a cold exposure control plan and, below an equivalent chill temperature of −7 °C, a nearby heated shelter; the national centre also advises scheduling heavy work in the warmer part of the day and a buddy system.
- Plan snow and ice: who clears it, where it goes (never on laydown, fire routes or drains), sanding, and lighting for short days.
- Keep winter items separate in the estimate and schedule, check them against the forecast each week, and record the days weather stops work.
Checklist
Before the first cold week
- Sensitive work listed with its minimum conditions
- Enclosures and heat assigned, priced and ordered
- Heater type, ventilation and carbon monoxide testing planned
- Cold-weather concreting agreed with the engineer
- Cold-stress plan and warm shelter ready
- Snow clearing and storage assigned
Check your understanding
Why is "winter conditions: $40,000" a weak line in an estimate?
Show the answer
Sources
- Cold Environments – Control Measures
- OHS Regulation Part 7: Noise, Vibration, Radiation and Temperature (sections 7.33 to 7.36, Cold exposure)
- OHS Regulation Part 13: Ladders, Scaffolds and Temporary Work Platforms (section 13.11)
- Heaters (safety talk)
- 29 CFR 1926.154 Temporary heating devices
- CIP 27 – Cold Weather Concreting
- NMS table of contents (Division 01: 01 51 00 Temporary Utilities; 01 56 00 Temporary Barriers and Enclosures)