Recording a site video walkthrough that is useful later
A ceiling is due to close tomorrow, and the superintendent has time for one walkthrough. Last month's recording swings between rooms without saying where it is. The coordinator can see pipework but cannot match the footage to a room on the drawings.

Record one short, narrated route and identify the date, level and room as you enter each space. Start and finish at recognizable points, then save an index with the file. A video is useful when another person can follow your route without remembering the job. Length alone does not make it a better record, and narration cannot rescue footage that never shows the subject.
- Choose the question the recording should answer: what was above the level 2 ceiling before it closed, for example. Mark the route on the current room plan and split unrelated areas into separate recordings.
- Walk the route first. Arrange permission and safe access, clear the view where practical, and check for conversations or personal information that should not be recorded.
- At the start, say the project identifier, capture date, level and stage of work. At each doorway, say the room number before moving toward the feature you want to show.
- Pause at services, junctions and access provisions. Describe what is visible and the direction you are facing; record uncertainty as uncertainty instead of guessing what a component does.
- Play back a sample before leaving the area. Check that the picture and your voice are usable, then upload the original to the project record with the route plan.
- Write a short timestamp index for important rooms or observations. Add separate close-up photos where a label or connection cannot be read in the video.
Common mistakes
- Talking while turning quickly, so the narration describes a view the viewer has already lost.
- Calling a space 'over here' instead of using the room identifier.
- Saving only a compressed message attachment and losing the original recording.
- Making one long recording that mixes levels, dates and unrelated issues.
Checklist
Before the route is covered
- One recording purpose
- Start point and route on the plan
- Spoken date, level and room identifiers
- Readable close-ups saved separately
- Original file in the project record
- Timestamp index checked by another person
Check your understanding
Your video clearly shows a service junction, but no room number is spoken. How should you make the record usable?