How to document concealed work before it is covered

By Review.LivePublished 3 min readHow we write

Two years after handover, the facility manager calls: a tenant wants a new doorway in the level 3 corridor, and nobody knows whether the sprinkler line runs through that wall. The photos from the week before drywall show pipe in close-up, with no room number, gridline or tape in the frame. The wall will have to be opened.

Open stud walls in a gutted brick building with capped plumbing stubs, electrical boxes and armoured cable before drywall.
Photo: Olek Buzunov on Unsplash

Concealed work — services in walls and ceilings, firestopping, reinforcement in slabs, pipe below grade, membranes behind cladding and under tile — can be shown after cover only through the record made before it. Those records usually fail the same way: whoever knows the room photographs the detail, not where the detail is. Some owners require the record: one university's photo standard asks for every wall and ceiling rough-in to be documented after inspection and before concealment.

Photograph it for a stranger

  1. Name who records each area that closes tomorrow: walls before board, decks before a pour, trenches before backfill.
  2. Shoot after the inspection and corrections, just before cover, so the photos show the accepted work.
  3. Fix the location first: a wide shot with a room number, gridline tag or level marker, then overlapping frames along the whole wall, deck or trench, and a pin on the current drawing: a geotag cannot say which wall or floor.
  4. Measure from fixed points: a tape from a gridline, corner or floor to each box, pipe and sleeve; below grade, the depth from a known elevation.
  5. Show what was checked, close and well lit: laps, fasteners, pipe markings, firestopping labels, bars and their chairs.
  6. Report differences from the drawings the same day, in writing and with photos, to the general contractor (GC) or the design team; if one means extra work, record its time and material.
  7. Describe and file the set before cover: a line per photo saying what it shows, every wall present and readable, originals kept, and the set attached to the area's inspection or report.

Common mistakes

  • Shooting while trades are still working, so the photos show work that later changed.
  • Starting after the first sheets of board are up.
  • Recording what was installed but not what differs from the drawings.

Checklist

Before the area is closed

  • One person named for each closing area
  • Photos taken after the inspection, just before cover
  • A wide shot first, then overlapping frames
  • A tape from a fixed point to each service
  • The set pinned on the drawing, each photo described
  • Differences from the drawings sent in writing
  • Originals kept and the set filed before cover

Check your understanding

Your photo shows a pipe clearly but nothing around it. What is missing, and why does it matter after cover?

Show the answer
The place is missing: a wide shot that shows the room or gridline, and a tape from a fixed point to the pipe. After cover, the reader has the drawings but not the site, so the photo must say where as clearly as what.