Recording equipment on site: every machine, whose it is, and whether it worked today
The rain-week report lists two excavators and a loader every day. One excavator actually left on Tuesday, while the loader continued moving stockpiles. The list looks complete until someone uses it to explain a full week's standby charge.

Keep one identifiable line per machine and update its observed status during the day. Record whose equipment it is, where it was and whether you saw it working, waiting or out of service. Presence on site does not establish operating hours, billable rental time or entitlement to a standby payment.
Track machines rather than descriptions
- Give each machine a stable identity. Use the fleet or rental number where available, with type and owner. Two similar excavators need separate lines. Link the delivery record and arrival date, and record departure against the same identity rather than deleting the line.
- State what you observed and when. Write the location, task and observation time. 'Loader L-04 moving aggregate at 09:40' is useful; 'loader worked' leaves the duration uncertain. Use additional observations or the operator's attributed report when activity changes.
- Explain a status carefully. Separate working, waiting and out-of-service states under your chosen definitions. Record a known reason and its source, such as a repair ticket or the foreman's report. If the reason is unknown, say so instead of selecting the cause that suits the account.
- Close the day's movement. Check arrivals, departures, transfers and replacements against delivery or pickup records. Link relevant task, weather or delay entries. Carry an unresolved condition forward with a fresh dated observation rather than automatically copying yesterday's status.
This register can be simple without pretending to measure use. If the commercial review needs meter readings, operator hours, rental terms or an agreed standby record, obtain those separately. Ask the office what supporting record it needs before the event becomes old. Keep any later explanation dated and preserve the original daily observation.
Common mistakes
- Copying yesterday's list after a machine leaves.
- Recording a breakdown as weather standby without a confirmed reason.
- Multiplying machines present by shift hours and calling the result measured use.
Checklist
Complete the equipment line
- Stable machine number, type and owner.
- Arrival and departure references.
- Time, location and observed activity.
- Status reason and its source, or unknown.
- Separate supporting records for any hours or cost review.
Check your understanding
Does a loader on the site list establish a full day's standby?