Preventing conflict with clear expectations at the pre-construction meeting
On your last job with this owner, their facilities manager emailed trades directly, approved a colour change nobody had priced and expected an answer to every message within the hour. The next project with the same owner starts in three weeks. The pre-construction meeting is on Thursday, and the agenda is still a blank page.

A lot of conflict on a job starts as two sets of expectations nobody said out loud: how fast questions get answered, who may give an instruction, when the site is open, what counts as a change. The pre-construction meeting is the cheapest place to find those gaps, because nothing has gone wrong yet and nobody is defending a position. Run it as a working session that ends in written agreements, not only as introductions.
- Name who speaks for whom: one contact each for the owner, the consultant and your company, and who may give an instruction or approve a change.
- Agree the communication rhythm: the weekly meeting, the report, the channel for urgent problems, and response times for requests for information and submittals, using the contract's times where it sets them — see a client communication plan.
- Settle access and site rules: working hours, deliveries, parking, occupied areas, noise and keys.
- Map the approvals: submittals, samples, mock-ups and inspections, with who approves each and how long it takes.
- Walk through how changes work under your contract: request, price, written approval, then work — and what happens when something urgent cannot wait.
- Agree how problems go up when the site level cannot solve them, and who talks to whom at each step.
- Put it all in the minutes and ask every party to confirm them within a week.
Common mistakes
- Spending the meeting on introductions and leaving the hard topics for later.
- Agreeing response times your team cannot keep.
- Leaving the change process to "the contract" without walking through it.
- Not recording the agreements, so each party remembers its own version.
Checklist
Put these on the agenda
- Contacts, and who may instruct or approve
- Meeting and report rhythm, and response times
- Hours, deliveries, access and site rules
- Submittals, samples, mock-ups and inspections
- The change process, step by step
- The escalation path
- Minutes confirmed by every party
Check your understanding
The owner says the contract already covers all of this. Why spend meeting time on it?