RFIs that get answered: one clear question with a proposed answer
RFI 27 went to the architect on a Tuesday: "Please clarify the detail at the stair." Nineteen days later the reply asked which stair, which detail and what was unclear. By then the framers had worked around the stair opening twice.

A request for information (RFI) is the formal written question a contractor sends when the contract documents are unclear, incomplete or in conflict. Washington State's transportation department calls it the procedure for officially requesting an explanation or interpretation of the contract, and expects ambiguities to be raised as soon as they are found. RFIs stall when the reader has to work out the question: vague wording, several questions in one, no reference and no date.
- Check before you ask. Search the drawings, specifications, addenda and earlier RFI answers; the answer is often already there.
- Ask one question, worded so it can be answered with yes, no, a dimension or a choice.
- Give the exact reference: sheet and detail, gridlines, specification section. Attach a marked-up drawing or a photo.
- Propose an answer: "We propose 200 mm, as shown on S-301. Please confirm." A clear proposal can be confirmed, corrected or rejected quickly.
- State the date you need the answer and what it holds up: "Needed by June 12 to release stair formwork on June 15."
- Send trades' questions through the general contractor, number every RFI in sequence and log the dates sent, due and answered.
- Review open RFIs every week, and chase the ones close to their needed-by date.
Common mistakes
- Bundling several questions, so the answer covers only one of them.
- "Please advise" with no proposal and no reference.
- Using an RFI to announce a delay or a claim.
- Asking a question the specifications already answer.
Checklist
Before you send an RFI
- The answer is not already in the documents, addenda or earlier RFIs
- One question
- Sheet, detail, gridline or section named
- Marked-up drawing or photo attached
- Your proposed answer
- The date needed and what it holds up
- Numbered and logged
Check your understanding
Why include a proposed answer when the design is the consultant's responsibility?