Skip to content

Coordination

Coordinating mechanical and electrical routes on smaller projects

By Review.LivePublished 3 min readHow we write

The ductwork shop drawings arrive on Monday, the sprinkler layout on Wednesday and the electrical layout not at all. There is no 3D model and no budget for one, and the corridors have 450 mm between the underside of the beams and the ceiling grid. Installation starts in three weeks.

Steel conduits, a grey cable raceway and a red sprinkler pipe run side by side under a concrete waffle slab.
Photo: Nopparuj Lamaikul on Unsplash

On design-bid-build work the engineer's mechanical and electrical drawings are usually diagrammatic: they set the scope and materials but not the exact layout, so each trade routes its own system. A Stanford University research paper describes the traditional check: the trades meet to overlay their drawings, draw sections where space is congested, decide who moves, and send the problems that need the engineer as requests for information (RFIs).

  1. Collect every trade's layout at one scale on the structure and reflected ceiling plan, with sizes and bottom elevations including insulation, hangers and supports.
  2. Overlay in order of flexibility: ductwork first, since it is largest and has the fewest places to go, then the heating and cooling piping that serves it, then gravity drainage, which must keep its slope; pressure piping, sprinklers and electrical last.
  3. Draw sections at the tight spots: beam crossings, shafts, and anywhere three systems meet.
  4. Mark each clash and decide who moves, with the foremen or detailers in one meeting; the more flexible system usually moves.
  5. Send design questions as RFIs: a change to a size, slope, fire separation or structural penetration is the designer's call — see RFIs that get answered.
  6. Mark what must stay reachable: access doors, valves, dampers and service space.
  7. Have each trade sign the layout, then walk the space with the foremen and mark main routes on the deck before hangers go in.

Common mistakes

  • Letting the first trade on site set the routes.
  • Overlaying without insulation, hangers and fittings, so the drawing clears and the ceiling does not.
  • Plans only, with no sections at the crossings.
  • Settling a design question on site without the engineer.

Checklist

For the coordination meeting

  • Layouts at one scale, on one background
  • Bottom elevations with insulation and hangers
  • Overlay starting with ductwork and drainage
  • Sections at every tight crossing
  • One trade assigned to each clash
  • Design questions sent as RFIs
  • Access doors and service space marked
  • Signed layout and routes marked on the deck

Check your understanding

Why start the overlay with ductwork and gravity drainage rather than the electrical layout?

Show the answer
Large ducts have only a few places to go, and a drain must keep its slope end to end, so they leave the least room to adjust. Conduit and cable are the easiest to reroute, so setting the rigid systems first avoids moving the same duct or pipe twice.

Sources

  1. MEP Coordination in Building and Industrial Projects (CIFE Working Paper 54)Center for Integrated Facility Engineering, Stanford University · accessed
  2. Master Construction Specifications, Section 01 31 00: Project Management and CoordinationUniversity of Houston · Texas, United States (one owner's master specification; check your own specifications) · accessed