The daily coordination board: every trade's area and the shared resources, hour by hour
At 9:40, the painter and electrician both expect the fourth-floor corridor. The hoist is also requested by two trades at ten. The superintendent needs one current view of the day's areas and shared resources, with a clear way to change it.

Put areas down the board and the day's time blocks across it, with separate rows for shared resources. Show each trade's planned location, booking and current status. Give updates a named owner and backup, and confirm changes with affected people. A colour on a board is a coordination record, not a permit, qualified lifting plan or proof that an area is ready. Keep those prerequisite decisions linked and visibly unresolved where necessary.
Make the day's working map readable
- Choose stable areas and useful time blocks. Use floor, room or zone names the trades recognize. Add hoist, crane, loading and other shared-resource rows. Pick a planning interval that suits the day; do not imply every activity or safety process can be reduced to an hourly reservation.
- Record trade and booking details. Show the responsible contact, task and intended time, using colour plus text or symbols people can distinguish. Identify deliveries and inspection windows. Separate a request, confirmed booking and pending approval so an uncertain entry does not look like a completed decision.
- Check interfaces before posting the plan. Compare adjacent tasks, access and shared-resource demands with the affected foremen. Link any required technical, safety, shutdown or readiness review. A crane slot or shutdown block stays conditional until its separate requirements are satisfied through the proper process.
- Control updates with a named route. Have the authorized board owner or backup record agreed changes and their time. Notify affected trades directly for important changes; moving a magnet may not reach a crew already working. Immediate hazards still use the safety process without waiting for a board editor.
- Close and roll forward the board. Confirm actual status and remaining needs before preparing tomorrow's view. Retain the appropriate dated record without pretending it proves every event on site. Remove stale bookings and transfer unresolved approvals to a named follow-up owner.
Common mistakes
- Using colour without a readable legend or contact.
- Making a request look like an approved booking.
- Moving a resource block without notifying the affected crew.
Checklist
The daily board's minimum information
- Recognizable areas and time blocks.
- Trade, task and responsible contact.
- Shared-resource requests and status.
- Readiness and approval links.
- Named update owner and backup.
- Dated changes and direct notifications.
Check your understanding
The fifth-floor cell is empty. Can the painter treat it as a released work area?