Hold points for waterproofing: where the work stops until someone has looked
The waterproofing foreman expects a wall to be ready this afternoon. Backfill is booked for the morning, but the review list does not say which person releases the before-cover hold. A photograph has been sent to the project group without a clear request for that decision.

Make each required hold a located decision with a named release role. Identify the actual project requirement, give the agreed notice and retain the resulting decision before the next stage proceeds. A photograph or completion message supplies evidence; it does not by itself satisfy an acceptance role. The register should let the incoming trade see which boundary is released and which remains conditional.
Put the release decision beside the work stage
- Read the actual inspection requirements. Collect the project’s inspection and test plan, specification and agreed review arrangements. Separate mandatory holds, witness opportunities and routine crew checks according to those documents. Avoid adding an invented consultant sign-off to every stage or treating a required hold as optional because the crew has checked itself.
- Locate each affected stage. Identify the zone, detail and next operation that will reduce access. A register might address receiving substrate, selected interfaces or before-cover work when required. Describe the actual boundary so a hold on one wall is not accidentally interpreted as a site-wide release or a site-wide stop.
- Name notice and decision roles. Confirm who requests the review, who receives the evidence and who can release the hold. Record the actual notice arrangement and availability. Sending a group message to several people can leave everyone assuming someone else will supply the required decision.
- Prepare the receiving evidence. Identify the current references, located photographs, test reports and resolved-detail information needed for that review. Keep incomplete items visible. A package marked ready should explain its exceptions rather than relying on the reviewer to discover that one penetration remains unresolved.
- Record findings and disposition. Link the review to its location, decision and remaining actions. Assign correction and the required follow-up review. Keep accepted scope distinct from a report’s general comments; a visit record may identify an issue without releasing work affected by it.
- Hand over the released boundary. Confirm the incoming trade receives the actual decision and restrictions. Update the register after damage, changes or revised conditions that need another assessment. A prior release should not hide a later concern simply because the original check box remains green.
Common mistakes
- Leaving the decision unnamed in a group conversation.
- Reporting readiness while hiding an unresolved interface.
- Keeping an old release green after relevant damage.
Checklist
The located release line
- Actual requirement and review type.
- Zone, detail and next-stage boundary.
- Notice owner and release authority.
- Complete evidence with stated exceptions.
- Findings, corrections and follow-up decision.
- Incoming trade’s current release information.
Check your understanding
The crew’s checklist is complete, but a separately required before-cover release is still missing. Can the incoming trade use the checklist as that release?