When the owner asks you to finish early
On a Monday call, the owner of a new exhibition hall asks whether you can hand it over on 8 May, two weeks before the contract date, because a regional trade show wants it from 9 May. "Put more people on it," she says. "We'll sort out the money after the show."

Treat it as a change: find out what must be ready and why, price the extra resources, and seek a signed agreement on price, dates and the owner's obligations before extra shifts start. If your contract permits a written direction before price is agreed, follow its procedure and keep separate records. US federal fixed-price construction contracts, for example, list directing acceleration among changes the contracting officer may order in writing, with an equitable adjustment when cost or time changes.
- Ask what the date is for: which areas, which use, what finish.
- Work back from it: the critical path, the activities that must shorten, and any inspections and occupancy approval the building authority requires.
- Price every cost of going faster — a second shift or overtime, supervision, lighting, security, cleaning and lost output — as a cost per day gained.
- List the owner's conditions, with dates: decisions, approvals, access, its other contractors.
- Sign the change before the extra shifts start: the price, the areas and their new dates, whether a new date replaces the contract date and anything tied to it, such as liquidated damages, and what happens if a condition slips.
- Get each trade's priced commitment in writing, and track the work under its own cost code.
Common mistakes
- Starting extra shifts on a phone call and pricing them later.
- Promising the whole building when the owner needed part of it.
- Accepting a date with no conditions on the owner's decisions and inspections.
Action list
When the owner asks for an earlier finish
- Ask what must be ready, and why
- Work back from the requested date
- Price each cost, per day gained
- Name the owner's conditions and dates
- Sign the change before extra shifts start
- Track cost and progress separately
Check your understanding
The owner's representative says: "Start the evening shift Monday; the change order will follow." What do you reply?