When the general contractor's schedule does not work for your trade
The general contractor's baseline arrives on Tuesday with a note: "Please review and confirm by Friday." Your mechanical rough-in on level 3 is a single 10-day bar between framing and the ceiling grid. Your foreman looks at it once and says it is a 15-day floor.

Before you confirm, check your own activities: each duration against your quantities and crew, what must be finished before each starts, and what follows. Then send one written reply that lists each problem with its basis and a proposal. Trade durations are often squeezed until the finish meets the contract date, and once you accept the schedule, a slip against it looks like your delay. The Lean Construction Institute's test of a reliable promise applies: the person promising has estimated how long the task will take and is not privately doubting they can deliver.
- Ask for your activities with their logic: predecessors, successors and dates, not only the bar chart.
- Check each duration against your quantities and crew, as in durations from quantities, and whether the area can hold that crew.
- Check what must come first: structure, framing, openings, other trades' mains, and your own approved submittals and equipment lead times.
- Check what follows and who shares the area: the next trade, the inspection before cover, and how many trades share those days.
- Reply in writing before you confirm, one line per problem: the activity, what the schedule shows, what you need and why, and a proposal: a longer duration, another sequence or the condition under which the date works.
- If the dates stand, confirm your assumptions in writing, such as when each area is handed over, and record when it actually was.
- Check your activities in every update.
Common mistakes
- Confirming, or signing the subcontract, without reading your activities.
- Objecting without a basis or a proposal.
- Raising it only by phone.
- Promising the date and planning to add people the space cannot hold.
What to say
Your reply, one problem at a time
Check your understanding
The general contractor answers: "Everyone else accepted. Just add people." Four workers already fill the ceiling space. What do you reply?