Taking over a project halfway: the first two weeks

By Review.LivePublished 3 min readHow we write

It is your first morning on a job seven months into an eleven-month schedule. Your predecessor moved to another project on Friday, leaving a one-page note, a shared drive and a promise to answer his phone. The owner's representative wants to meet on Thursday.

A clipboard headed Open Projects lies beside a laptop and pen.
Photo: Markus Winkler on Unsplash

Start with anything that has a clock on it — notices, change requests, payment dates and permits due soon — because those can be lost while you are still reading. Then work through the contract, the money, the schedule, the open issues and the people in a planned order, and report what you found by the end of week two. A handover note holds what your predecessor remembered; the risk sits in what they did not know was unfinished, such as a priced change never sent or a notice period quietly running.

The first ten working days

  1. Days 1–2: find the clocks. List every deadline in the next 30 days — notices, unsent change requests, the next payment application, permits, inspections — and act on anything due this week.
  2. Days 2–3: read the contract or its summary for notices, changes and payment — see reading the contract.
  3. Days 3–5: rebuild the money: budget, cost to date, commitments, forecast, billing, holdback, and every change by status, drafts included.
  4. Week 1: walk every area with the superintendent against the schedule, and read a month of daily reports and notes for instructions nobody passed on.
  5. By the end of week 2: meet the owner's representative, the consultant and the key trades; ask what each is waiting for and was promised.
  6. Day 10: send your manager a takeover report: what you found, what is at risk, what you did and what you need.

Common mistakes

  • Reading the files in order while a deadline runs out.
  • Trusting the last forecast or schedule update without walking the site.
  • Assuming that what is not in the files did not happen.
  • Criticizing your predecessor to the owner or the trades.

Checklist

Ask your predecessor on day one

  • What have you promised anyone that is not in writing?
  • Which changes are priced but not sent?
  • Which notice, claim or payment dates are running?
  • Who on the owner's side really decides?
  • Which trade worries you most, and why?
  • What would you do first if you stayed?

Check your understanding

On day three a subcontractor says your predecessor agreed by phone to pay for two Saturdays of overtime. Nothing is written. What do you do?

Show the answer
Neither accept nor reject it yet. Ask the subcontractor for their record and your predecessor what was agreed, and check whether it reached the owner; then answer in writing by a date you set. Treating it as unknown until checked protects the relationship and the money.