A five-number project dashboard: one line that tells your management how the job is
Your director asks how the job is doing. You have a cost report, a bar chart and three lists, each with a different date. A green overall status would be easy to send, but it would conceal the cash issue that needs a decision.

Use a five-number project dashboard as an entry point to the job: forecast margin against its starting budget, schedule movement against the baseline, cash billed versus collected, the value of unresolved changes, and overdue open items. Define and source each measure, then update it from the weekly controls cycle. Put a short explanation and requested decision beside an important movement. The numbers invite a useful review; they do not replace the supporting records.
Make five measures comparable
- Define the margin comparison. Agree the company’s forecast method and whether the dashboard shows dollars, percentage points or both. Record what costs and revenues are included. Never mix an approved contract value with speculative change revenue without explaining it.
- Choose the schedule reference. Show the approved comparison date and the current forecast for the same milestone. Describe working days or calendar days explicitly and retain the baseline reference so a revised target does not erase the movement.
- Show cash status accurately. Keep billed and collected amounts separate with a common cutoff. Explain material unapplied receipts or disputed applications. A billing total is activity; it is not proof that the customer has paid.
- Separate unresolved change exposure. Define whether the figure covers submitted prices, estimated costs or both. Keep approved changes out of the pending measure and link the record used to avoid double counting.
- Count overdue items against real due dates. Choose the action list and definition, such as unresolved decisions past the agreed date. Add a short note for the items controlling work; ten minor actions do not automatically matter more than one critical decision.
- Attach the movement and the ask. Date the dashboard, identify each source and compare like with like. State the decision or support needed when a measure moves, rather than allowing a colour to stand in for an explanation.
Common mistakes
- Using traffic-light colours without definitions or supporting dates.
- Resetting the baseline so schedule movement appears to disappear.
- Presenting requested change value as approved income.
Action list
For each dashboard measure
- Define what it includes.
- Name the source and cutoff.
- Compare the same basis over time.
- Explain material uncertainty or movement.
- Show the decision the reader needs to make.
Check your understanding
The overdue-item count falls because several due dates were moved. Does that prove the job improved?