Coordinating consultant field reviews: notice, sequence and what each discipline needs

By Review.LivePublished 3 min readHow we write

A consultant is called after the crew says the work is ready to cover. The visit cannot be arranged in time, and the next activity is waiting. The look-ahead named the work but omitted the review and the preparation it needed.

New steel beams with a bolted splice sit on temporary adjustable steel props in a house extension under construction.
Photo: Brett Jordan on Unsplash

Build a field review calendar with the responsible consultants, identifying the stages they need to see, how notice is given, what must be ready and accessible, and who accompanies the visit. Use the look-ahead to book and update reviews before the work reaches them. Keep the consultant’s professional review scope separate from the contractor’s quality control and other required inspections. Confirm the actual requirements with the relevant professional and project documents.

Put the review into the work sequence

  1. Confirm the review arrangements by discipline. Ask the responsible consultant about anticipated stages, information and notice. In British Columbia, EGBC’s guidance leaves the number and extent of engineering field reviews to the professional’s discretion; a contractor’s calendar must not impose a fixed limit.
  2. Link each visit to a work location and stage. Show the activity before the review and what follows it. Include relevant hold points from the project’s requirements, with a named person responsible for confirming readiness.
  3. Prepare the visit package. Provide current drawings, relevant approved information and the questions needing attention. Identify unresolved deviations rather than presenting an incomplete area as accepted work.
  4. Arrange access and attendance. Confirm the time, site arrangements and person walking with the reviewer. Follow the site’s safety procedures and explain any inaccessible location before the visit rather than improvising access on arrival.
  5. Confirm changed readiness promptly. If work moves or the stage is not ready, notify the consultant and affected team through the agreed route. Record a revised arrangement and keep subsequent work dependent on the applicable release conditions.
  6. Follow the report through to closure. Assign each observation or question to its responsible person, record the response and arrange any return review requested. A visit completed on the calendar is not proof that every follow-up item is resolved.

Checklist

For each planned review

  • Responsible discipline and current contact.
  • Work location, stage and readiness owner.
  • Confirmed notice and required information.
  • Safe access and accompanying person.
  • Report actions and any return review.

Check your understanding

The calendar says the consultant visited, but the report asks for a return check. Is that stage closed?

Show the answer
Keep the return check and any associated release condition open until the responsible professional confirms the required outcome. Update the work plan and tell affected trades what remains unresolved. Recording attendance and recording closure are different controls.

Sources

  1. Guide to the Standard for Documented Field Reviews During Implementation or Construction, Version 4.0Engineers and Geoscientists BC · British Columbia, Canada; EGBC professionals · accessed