A purchase order that prevents disputes
A door delivery arrives with the right overall quantity but mixed floor bundles. The buyer expected prepared openings for the scheduled hardware, while the supplier read the order as standard doors only. Both point to a brief description copied from the estimate.

Write the purchase order so another person can identify exactly what to supply, when to deliver it and which documents and terms apply. Reference current requirements without leaving the supplier to guess which version you mean. A clear order becomes the receiving team's comparison record. It also exposes unresolved choices before they become disputes on the loading dock.
- Identify the supplier, project, delivery address and authorized buyer. Describe each item with the required model, specification reference, current approved information and any agreed exclusions.
- State quantities and units clearly, including package quantities and whether accessories are included. Reconcile the order with the checked takeoff instead of converting bundles or pairs from memory.
- Define the delivery sequence and dates with the superintendent and supplier. Give the required labels, packaging, access arrangements and contact for each delivery rather than writing only 'deliver to site'.
- Record the agreed price basis, freight, taxes, payment terms and how proposed changes must be authorized. Show which terms have been negotiated and refer conflicts to the person authorized to resolve them.
- List required documents and identification: relevant certificates, instructions, reviewed details and product labels. Specify when the records must accompany the goods or arrive separately.
- Confirm return conditions, damaged-goods handling and cancellation arrangements before issue. Obtain the supplier's acknowledgement and give the receiving foreman the final order and any accepted amendment.
Common mistakes
- Using a quotation number without identifying which revision was accepted.
- Writing 'complete' when the accessory scope is still disputed.
- Assuming a supplier's standard return policy applies to custom goods.
- Changing delivery dates by phone without updating the receiving team's record.
Checklist
Check the order before release
- Exact product and revision
- Quantity and unit
- Accessories and exclusions
- Delivery sequence and labels
- Price and change authority
- Documents and return terms
Check your understanding
The supplier acknowledges your order with a different delivery date. Is silence a safe way to resolve it?