Recovering from a disruption: the first 48 hours

By Review.LivePublished 3 min readHow we write

The superintendent arrives at 06:30 after an overnight windstorm: the east wing's temporary roof is torn open, rain is still coming in and the site has no power. Crews arrive at 07:00, ready to clean up. The owner's representative has already texted, asking for a new completion date.

A steel-framed building with its metal cladding torn and bent, and sheet metal and lumber scattered on the ground around it.
Photo: Strange Happenings on Unsplash

The first two days after a storm, flood, fire or outage decide how large the loss becomes. Crews want to start cleaning, the owner wants a date, and the evidence of what happened disappears as people work. A short, ordered plan protects people first, stops further damage, and makes the record while it can still be made.

  1. Make it safe first: account for everyone, keep people out of affected areas until competent people have checked electrical, structural and fire hazards, and call emergency services if needed.
  2. Report what the law requires: if anyone is hurt, or the event itself is reportable, your jurisdiction decides who is told, how fast and whether the scene must be left alone.
  3. Stop further damage, and only that, once the area is cleared: shut off water, cover openings, pump out and secure the site, with fall protection used on the roof and damaged circuits isolated first.
  4. Record before you clean: photos of every affected area with time and location, a written account, the weather record and a list of damaged work and materials. Keep damaged items until the owner and the insurer release them.
  5. Notify the same day: the owner or consultant in writing under the contract's notice clause, your insurer or broker, and every affected trade.
  6. Replan on day two: what continues elsewhere, what must be redone, what needs reordering, and a recovery look-ahead with owners and dates.
  7. Track recovery costs separately from the first hour, under their own cost code.

Common mistakes

  • Cleaning up before anything is photographed.
  • Throwing out damaged material before the adjuster has seen it.
  • Telling the owner by phone and never in writing.
  • Promising a new completion date on the first day.

Action list

In the first 48 hours

  1. Account for everyone; get the hazards checked
  2. Report what your rules require
  3. Stop further damage, nothing more
  4. Photograph and list the damage before cleanup
  5. Notify the owner in writing; call the insurer
  6. Issue a recovery look-ahead by day two
  7. Code recovery costs separately

Check your understanding

Why record the damage before cleanup starts, when everyone knows what happened?

Show the answer
Because the owner, the insurer and perhaps a court will need to know how much was damaged and why, not only that a storm happened. Once cleaning starts, the extent disappears. A dated record made before anything is moved supports the claim and the revised schedule.