Tracking rework hours so the causes can be fixed

By Review.LivePublished 3 min readHow we write

Eight weeks into an office fit-out, the interior contractor's framing and drywall hours are 9 per cent over budget. The foremen say crews have been rebuilding meeting-room walls, but every hour sits under a base-work code. Nobody can say how many hours went into doing work twice, or why.

New metal partition framing beside exposed timber and brick inside a building under renovation.
Photo: Olek Buzunov on Unsplash

Give rework its own code, make every entry carry a cause from a short list, and total the hours by cause each week; the one or two causes behind most of the hours are where to act. A rework code alone shows how much was done twice; the causes show what to fix. A Construction Industry Institute research team defined field rework as repeating field activities or removing work already installed on the project. Read literally, that includes work redone for an owner's change: keep those hours on the change's code, where they can be priced, and count the rest here.

Setting up the count

  1. Open one rework code, defined in one line: hours spent removing, redoing or repairing installed work that was wrong or damaged. Setting up codes is covered in cost codes field staff can use.
  2. Write six to eight causes that do not overlap: superseded drawing, layout error, installation error, damage by another trade, defective material, design conflict, and other with a note.
  3. Record at the source, the same day: hours, cause, location and a line of description, with photos when another trade did the damage.
  4. Total the hours weekly by cause, largest first, and as a share of all labour hours.
  5. Act on the biggest cause with a short cause analysis, and change the process, not only the wall.
  6. Pass recoverable hours on: damage by others and design conflicts go to the project manager for a back charge or a change request.

Common mistakes

  • A rework code with no cause, so the total rises and nobody knows why.
  • A cause list so vague that most hours land in "other".
  • Recording rework only when it is big enough to argue about.
  • Using the numbers to blame a crew instead of fixing the process.

Checklist

Your rework count

  • One rework code, defined in one line
  • Six to eight causes that do not overlap
  • Hours, cause and place entered daily
  • Change work on its own codes
  • A weekly total by cause
  • One action on the biggest cause

Check your understanding

Rework fell from 5 to 3 per cent of hours this month, but damage by other trades doubled. Is the job improving?

Show the answer
Partly. Your own errors are falling, which is what the count is for, but damage by others needs a different fix: protection, sequencing or a talk with that trade, and records for a back charge. Read the causes, not just the total.

Sources

  1. An Investigation of Field Rework in Industrial Construction (RR153-11, 2001): publication pageConstruction Industry Institute · accessed