Getting a subcontractor to commit to crew numbers, and tracking them
Last Tuesday's coordination minutes say the electrical subcontractor will staff rough-in on levels 2 to 4 "as required". Rough-in has to finish before drywall starts in three weeks. On Thursday's walk you count four electricians, and there is no number to hold the trade to.

Ask each trade for a number, workers on site week by week for its work in the look-ahead; write it in the minutes, count the crew every day and raise any gap the same week. "As required" cannot be checked; a number can, and a daily count turns an impression into a fact both sides accept. The count comes before the conversation with a trade that is falling behind; your own crews' numbers belong in the weekly labour plan.
- Ask for a number per week from the person who controls the trade's crews, tied to its activities in the look-ahead.
- Test it against the work: the quantities, the trade's usual output and the dates. If six electricians cannot finish three floors by the drywall start, say so now.
- Write it in the minutes as a number and a period: "Electrical: 6 electricians on site, weeks 12 to 15."
- Count every day, the same way: from the sign-in record or a head count at a fixed time, by company, into the daily report.
- Compare every Friday: committed worker-days against actual, beside the work completed.
- Raise a gap in the same week: first with the foreman, then with the trade's project manager, with the daily numbers in hand.
Common mistakes
- Accepting "as required" or "enough to keep up" as a commitment.
- Counting by eye on the days you happen to walk the floors.
- Waiting for the monthly schedule update to raise a gap.
- Demanding more workers for an area your side has not made ready.
Action list
This week
- Ask every trade for a number per week
- Test each number against the work
- Write it in the minutes
- Count each trade's crew every day
- Compare committed and actual every Friday
- Raise any gap before next week's meeting
Check your understanding
A trade has met its committed head count every day, but its work is two days behind. What does that tell you?