The superintendent's weekly report to the office: what your own company needs to hear
The office reads the owner's polished weekly update and assumes the site has everything it needs. You are still waiting for a masonry decision and a frame purchase order. Neither request has a named responder or a useful due point.

Write your internal weekly report for the people who can support the site. Compare actual progress and staffing with the current plan, identify the misses, and state what the office must decide or supply next. Keep a consistent short format and sending time. Urgent safety, quality or commercial matters must use their immediate channels as well.
Give the office five useful parts
- Progress against the look-ahead. Name the planned tasks and actual stopping points by area. Explain a missed task with observed facts and the next prerequisite. Do not repeat 'on track' while omitting incomplete review, testing or access. Link the current look-ahead so the office knows the comparison's basis.
- Staffing against the plan. Summarize the observed or reported manpower by trade beside the agreed plan. Identify the time and source where the distinction matters. Explain a requested crew change and the ready work it would serve, rather than asking for more people without an assignment.
- Office actions and due points. State the problem, needed decision, authorized responder and practical consequence of a late response. Separate a confirmed decision from an outstanding request. Give the office enough context to act, with a link to the supporting issue rather than an unexplained attachment bundle.
- Next week's needs and concerns. List the purchases, information or support needed for the coming tasks, then summarize relevant safety and quality matters with their existing report references. Mark urgent items already escalated. Include other material concerns even if they do not fit neatly into a one-page target.
Finish with an action list the office can answer. Ask responders to confirm the decision or next step, and carry unresolved requests forward with their original dates. A meeting to discuss the report is useful only if it updates the action owners. Keep the owner's report separate: it has another audience and does not replace your company's candid resource and decision review.
Common mistakes
- Copying the owner-facing narrative without internal action requests.
- Reporting a requested purchase as an issued order.
- Waiting for the weekly report to raise an urgent safety or quality issue.
Checklist
Send an answerable internal report
- Actual progress beside the current plan.
- Staffing comparison and source.
- Office decision, responder and due point.
- Next week's purchasing and information needs.
- Safety and quality references, plus carried-forward actions.
Check your understanding
Should you remove an unresolved staffing request to keep the report on one page?