Recording subcontractor performance fairly during the job

By Review.LivePublished 3 min readHow we write

The roofer finishes with a difficult week, and the project manager wants to put 'do not use again' in the trade file. The superintendent remembers several good months before a late design revision disrupted the final areas. Neither has a clear record of the earlier work.

Close-up of a person's hands holding a clipboard and a pen, ready to write.
Photo: Vladislav Igumnov on Unsplash

Evaluate the trade monthly against a few agreed measures, with dated examples and a chance to correct factual errors. Separate the trade's performance from conditions it did not control. A useful record describes what happened and what followed, rather than assigning a reputation from the last argument. Consistent evidence lets the next project manager judge whether the same concern matters on a different job.

  1. At award, choose measures relevant to the subcontract: schedule commitments, quality, safety follow-through, required paperwork and cooperation. Explain what evidence you will use and who reviews it.
  2. At each monthly review, compare actual performance with agreed obligations. Point to dated look-ahead commitments, inspection records, meeting actions and document submissions.
  3. Record context beside the observation. Distinguish missing labour from an unavailable workface, and a slow response from a late or incomplete request.
  4. Discuss the draft evaluation with the trade's responsible manager. Correct mistakes, retain a disputed point as disputed, and record the trade's explanation without treating it as an automatic excuse.
  5. Agree an improvement action where needed, with an owner and review date. At the next evaluation, say whether the action happened and what evidence changed your view.
  6. At closeout, summarize the pattern for future awards. Identify the scope, size and circumstances in which the trade performed well or struggled instead of issuing an unsupported blanket verdict.

Common mistakes

  • Giving every trade the same score because difficult conversations take time.
  • Recording personality judgements instead of observable conduct.
  • Changing the rating scale halfway through the job.
  • Allowing one improvement promise to erase earlier failures without checking the result.

Checklist

Before you file an evaluation

  • Same measures as the previous month
  • Obligation and dated evidence identified
  • Conditions outside the trade's control recorded
  • Trade's factual corrections considered
  • Improvement action followed through
  • Future-award advice tied to a particular risk

Check your understanding

A trade misses its target, but your team released the work area late. How should the evaluation describe it?

Show the answer
Record the planned and actual release dates before judging the trade's output. Assess the commitments it could still meet, such as advising you of the revised sequence. The next award needs that distinction so a site constraint is not mistaken for a lack of capacity.