Photographs for a claim: preserving the sequence, context and gaps
One photograph shows a locked electrical-room door. The claim concerns five weeks of interrupted work, but the image has no caption or connected event record. The reviewer needs the sequence around the door, rather than one dramatic frame.

Photograph a disputed event as a located sequence, with an overview for details and captions explaining what was observed. Preserve the originals and connect the images to daily activity, notification, schedule and resource records. The photographs can support a claim review; they do not independently establish responsibility, continuous waiting, project delay or recoverable cost.
Record the event's visible sequence
- Establish the scene. Identify the location, affected work and observed condition in an initial overview. Add relevant detail from safe permitted access. Say what the image shows rather than naming a legal cause. Record the photographer, capture time and any uncertainty about the device's clock.
- Return at useful points. Capture material changes and, where practical, repeat the same viewpoint. Describe moved equipment, changed access or other work visible in the area. Do not imply that a daily photograph documents every intervening hour, or arrange people and machines to make waiting look more extensive.
- Link the accompanying facts. Reference the day's event entry, request, reply and resource record. State which task could not proceed and what the crew actually did instead. Keep observations and another person's explanation distinct; a caption is not a place to convert an allegation into a confirmed fact.
- Preserve a reviewable set. Retain original files and available metadata in approved storage. Verify dates and locations against other records where possible. Make an index with the file reference, caption and coverage gap. Use labelled working copies for arrows or explanation, keeping the originals unchanged.
Include relevant photographs that complicate the account as well as those that support it. A partly accessible area or an alternative task may matter to the analysis. Keep the search and selection process clear, and ask the company's appropriate advisers what further preservation and disclosure are required. Do not discard an awkward image to create a simpler story.
Common mistakes
- Leaving a close-up unconnected to its area and event.
- Editing the only copy or trusting unverified timestamps.
- Selecting images to imply continuous idleness while omitting alternative work.
Checklist
Index the event photos
- Located overview and relevant detail.
- Photographer, date and clock uncertainty.
- Repeated views and actual changes.
- Captions linked to event and resource records.
- Originals, working copies and gaps identified.
Check your understanding
Can an equipment photograph establish a day's compensable standby?