End-of-shift notes the next shift can use when the two foremen never meet
The night foreman arrives after the day foreman has left. A panel tag remains in the maintenance pit, materials are stacked beside unfinished work and an inspection is expected. A note saying 'carry on in pit three' leaves too much unexplained.

Leave a dated note in an agreed place that the next shift can access before assigning work. Cover where tasks stopped, restrictions, incoming deliveries or inspections, pending decisions and the detail you would explain face to face. Identify the writer and contact route, and ask the receiving foreman to acknowledge questions or changed conditions.
Use five short sections
- Work state. List the actual stopping point by location and task. Separate complete, incomplete and unverified work. Include the current drawing or instruction reference when it affects the next action. 'Pit three lighting incomplete; test status pending' is better than a percentage without meaning.
- Restrictions. Identify areas or equipment that must not be used and reference the controlling process. CCOHS guidance describes equipment-specific lockout procedures, training and authorized roles. A handover note records the restriction; it does not authorize another foreman to remove locks or declare hazardous energy controlled.
- Incoming events and decisions. State what is actually confirmed, its time and receiver. Mark an expected visit as unconfirmed if it is. List each unanswered question with its review owner, affected task and next contact, rather than leaving 'office knows' as the instruction.
- The spoken detail. Add the thing you would point out in person: a changed access route, a missing confirmation or a delivery location. Direct urgent safety information through the site's immediate reporting process as well. Do not rely on a note that someone may read hours later.
Check the previous note before writing the next one. Close resolved items with their actual confirmation, carry open items forward and identify new conditions. Keep the history rather than replacing yesterday's note. A photograph can help preserve an approved paper handover, provided it reaches the right repository and does not expose restricted information; it is not the only accessible copy.
Common mistakes
- Using 'finished' when testing or required review remains outstanding.
- Treating a note or photograph as permission to change energy controls.
- Leaving the handover in a locked trailer the receiving shift cannot access.
Checklist
Leave these five sections
- Task stopping points and locations.
- Restrictions and controlling references.
- Confirmed incoming events and receivers.
- Pending decisions and authorized contacts.
- One practical detail, plus receiving acknowledgement.
Check your understanding
The night foreman has read the panel note. May the crew resume electrical work?