Skip to content

Cost control

Preparing a monthly progress billing that gets paid

By Review.LivePublished 3 min readHow we write

It is the 24th, and the golf clubhouse billing is due to the consultant tomorrow. Last month's came back twice, first because the reviewer questioned the timber frame percentage, then because the statutory declaration was missing. The money arrived three weeks late.

An unbranded calculator and pen rest on a red notebook.
Photo: Recha Oktaviani on Unsplash

Bill the work in place at the cut-off date, line by line against the approved schedule of values, with backup a reviewer can check from a desk and every document the contract lists, and deliver it complete on the due date. Billings are paid late for predictable reasons: they arrive late, their percentages do not match what the reviewer saw on site, or a document is missing. Each one gets the billing sent back, cut or held, and the money arrives later than the contract promised.

  1. Set the routine at the start: cut-off date, due date, form, reviewer and the documents each billing needs.
  2. Walk the job at the cut-off with the superintendent and set each line's percentage from work in place, not from cost spent or the schedule's plan.
  3. Bill approved changes on their own lines, and stored materials only as the contract allows, with the proof it asks for, such as title and insurance.
  4. Check the arithmetic: previous total, this period, total to date, holdback, previous payments and amount due, with no line over 100 per cent.
  5. Attach the backup: dated photos by area, the updated schedule and a quantity sheet for any line that jumped.
  6. Add every listed document and send it on time, then diarize the payment date and any deadline for a notice of non-payment.

Common mistakes

  • Billing the schedule's planned percentage instead of the work in place.
  • Pushing a line ahead to cover a cash shortfall; reviewers notice and check every line after.
  • Folding unapproved changes into base-contract lines.
  • Sending it late, which can push payment into the next cycle.

Checklist

Before the billing goes out

  • Percentages from this month's walk
  • Approved changes on their own lines
  • Stored materials only with the required proof
  • Arithmetic checked, holdback shown
  • Photos, schedule and quantity sheets attached
  • Every listed document
  • Payment and notice dates in the calendar

Check your understanding

The schedule planned 85 per cent of the framing by the cut-off; the superintendent counts 70. The owner is used to the schedule's numbers. Which do you bill?

Show the answer
Seventy per cent. The reviewer checks the billing against the site, not the plan, and a percentage that is not there gets cut, delays approval and invites a line-by-line check next month. The gap belongs in the schedule update, with a recovery plan.

Sources

  1. FAR 52.232-27, Prompt Payment for Construction ContractsU.S. General Services Administration (Acquisition.gov) · United States (federal construction contracts) · accessed
  2. FAR 52.232-5, Payments under Fixed-Price Construction Contracts (materials delivered off site)U.S. General Services Administration (Acquisition.gov) · United States (federal fixed-price construction contracts; shown as an example) · accessed
  3. Statutory declaration (PWGSC-TPSGC 2835)Public Services and Procurement Canada · Canada (federal contracts; shown as an example of what a statutory declaration states) · accessed