Running a design coordination meeting with consultants during construction

By Review.LivePublished 3 min readHow we write

The consultant meeting has spent most of its time on an item that will not affect the site for months. A doorway detail needed for tomorrow’s layout has not been discussed. The minutes list questions, but nobody has agreed when a usable answer will be issued.

Two people point to different locations on a printed plan spread across a table.
Photo: ThisisEngineering on Unsplash

Run a design coordination meeting in the order the site needs decisions, with a named owner and an agreed issue date for each answer. Send the relevant drawings and a specific question before the meeting so the responsible consultant can prepare. The goal is not to read the entire request-for-information log aloud. It is to turn the next work front’s unresolved interfaces into decisions the site can actually use.

Build the meeting around the next work front

  1. Pick the issues from the look-ahead. Ask the superintendent which activities are approaching and what design information prevents preparation or installation. Distinguish an actual blocker from a general query.
  2. Prepare one clear question per issue. Include the location, current drawing references, photographs where useful and the interface that needs resolution. State the decision needed without prescribing an unapproved design solution.
  3. Invite the people needed to decide. Confirm which consultants and project representatives must be present. If an item involves several disciplines, name the person who will coordinate the combined response.
  4. Explain the site impact first. Describe which work cannot proceed and the required answer date. Let the responsible designer resolve the technical question while the project team explains its sequencing implications.
  5. Record the answer’s status. Separate a discussion, an agreed direction and a formally issued revision. Name who will issue the usable information and where the team will find it.
  6. Review overdue commitments before closing. Confirm changed dates and escalate decisions that threaten the work front. Circulate a short action record and check the issued answers before marking items closed.

Common mistakes

  • Closing an item because it was discussed, although the drawing needed by the crew is still missing.
  • Bringing a new interface to the meeting without giving the relevant consultant a chance to review it.
  • Combining several locations into one vague question and receiving an answer that covers only one.

Action list

For the next consultant meeting

  1. Identify the work front that needs an answer.
  2. Send the specific question and current references.
  3. Name the disciplines and response owner.
  4. Agree when usable information will be issued.
  5. Keep discussions separate from issued instructions.
  6. Close the action only after checking the response.

Check your understanding

The minutes say the ceiling detail is agreed, but the drawing has not been revised. Should the coordinator close the issue?

Show the answer
Keep the issue open until the information required by the site has been issued through the appropriate process and checked against the question. Record the discussion as progress, then confirm who will produce the usable reference and when.