Asbestos under Part 6: the survey, the licence, the certificates and the notice
An office-to-residential conversion receives a low quote for removing pipe insulation. The firm says its workers have experience but supplies no licence information. The project manager also cannot tell whether the survey covers the risers included in the proposed removal.

Keep assessment and contractor authorization separate. Part6 requires qualified asbestos risk assessment and work classification before the relevant disturbance or activity. The regulator’s employer guidance distinguishes contractor licensing from worker certification: abatement employers working for others require a licence, subject to the applicable exemptions, and workers need the appropriate certificates. Check the actual scope and current requirements; a licence does not answer every project-specific question.
Check the requirement against the actual work
- Compare the survey with the proposed disturbance. Mark the rooms, risers and services included in the work. Ask the qualified assessor about the report’s exclusions and any additional information needed. Keep unassessed areas visible in the tender record. Do not identify asbestos by appearance or direct a general worker to collect samples to fill a document gap.
- Verify the contractor’s actual authorization. Check the firm’s identity and current licence information through the regulator’s resources, including any relevant exemption question. Obtain the evidence for the contractor actually proposed, rather than relying on a related company’s name. Record uncertainties for resolution before accepting the package. Price and experience descriptions do not establish the missing licence status.
- Check the people assigned to the work. Ask the employer for the appropriate certificates and evidence supporting the proposed workers’ roles. Match names and scope rather than collecting an unrelated training roster. Keep replacements subject to the same review. Distinguish a worker’s certificate from the contractor’s licence so neither is used as a substitute for the other.
- Locate the task-specific documents and notices. Have the responsible qualified people identify the applicable plan, procedures, notice arrangements and completion evidence. Record their current versions and recipients. Ask how clearance and waste questions are addressed for this work, without prescribing a universal test or disposal method. A notice receipt records submission; it does not certify the work arrangement.
- Keep unexpected findings connected to the affected scope. Agree the contact and established response when the work encounters suspect material outside the assessed package. Record the location and obtain qualified direction before that area is treated as resolved. Update the affected instructions and employer information. Do not broaden a report’s coverage or relabel an unresolved finding to preserve the original price.
Common mistakes
- Substituting a worker certificate for a contractor licence.
- Assuming a building-wide title proves complete survey coverage.
- Treating a notice receipt as clearance or method approval.
Checklist
Review the asbestos package
- Actual disturbance scope and assessment limits.
- Contractor identity and licence status checked.
- Assigned workers and appropriate certificates.
- Current procedures, notices and completion questions.
- Qualified response for unexpected suspect material.
Check your understanding
The contractor is licensed. Can the manager close a survey exclusion?