Skip to content

Scheduling

Milestones that matter: intermediate dates a team can hit

By Review.LivePublished 3 min readHow we write

At the kickoff for a two-storey daycare, the draft schedule lists 58 milestones, from "Permit received" to "Paint touch-ups complete". Three months later nobody tracks any of them. The first date anyone notices is one already missed: the building closed in before the heating season.

Five tower cranes stand on top of a glass high-rise as its structure nears the top.
Photo: taro ohtani on Unsplash

A milestone is a point in time with no duration that marks a key event, and scheduling guidance advises using milestones only for major events or deliverables. On a building job the useful ones mark handoffs, the moments when one group's work lets others start, rather than the end of every task. Contract milestones can also carry money. Indiana's transportation department, for example, uses incentive/disincentive dates: finishing a specified part of the work early may earn extra payment, and finishing late may mean a credit to the department. Read what attaches to each contract date before choosing your own.

  1. Start with the contract's dates: interim completion dates, phased turnovers and access dates, and what attaches to each.
  2. Add the handoffs the job turns on, such as structure complete, closed in, permanent power on, rough-ins inspected, ceilings closed and systems started.
  3. Define done in one sentence for each. Lean planning guidance warns that a name like "dry-in" is not enough; describe what the work will look like on that date.
  4. Space them sensibly. The same guidance suggests intermediate milestones that break the work into phases of about 8 to 12 weeks.
  5. Give each milestone one owner who reports its forecast date every week.
  6. Track the forecast against the target. A forecast that slips two weeks running is your early warning, while there is still time to act.
  7. Use each milestone as the end point of a pull-planning session with the trades who will deliver it.

Common mistakes

  • A milestone for every task, so none stands out.
  • Names without definitions, so trades argue about whether a date was met.
  • Dates without owners.
  • Moving a milestone quietly when its forecast slips, so the warning is lost.

Checklist

For each milestone you keep

  • One sentence that defines done
  • The target date and what the contract attaches to it
  • One named owner
  • A forecast date, updated weekly
  • The trades whose work delivers it

Check your understanding

Why is "permanent power on" a better milestone than "electrical 50% complete"?

Show the answer
It marks a handoff that other work depends on, such as testing, heating and elevators, and on any given day it is either true or not. A percentage is an estimate that hides what is left and tells no other trade whether it can start.

Sources

  1. Schedule Assessment Guide: Best Practices for Project Schedules (GAO-16-89G)U.S. Government Accountability Office · accessed
  2. Recurring Special Provision 108-C-215: Critical Path Method Schedule (Incentive/Disincentive date)Indiana Department of Transportation · Indiana, United States (one public owner's contract specification) · accessed
  3. Last Planner System Standard Work (Pull Planning Session Invitation; Milestone Planning)Lean Construction Institute · accessed