Skip to content

Leadership and closeout

Closeout without chaos: the last month

By Review.LivePublished 3 min readHow we write

The owner's accountant replies to your latest progress claim: final payment and holdback will be released "once the closeout package is complete". Nobody on your team has a list of what that means. Substantial completion is four weeks away, and the site is still full of finishing trades.

A newly completed three-storey building with blue and silver metal panels and a glass entrance, seen across its plaza at dusk.
Photo: kaleb tapp on Unsplash

Closeout goes wrong when it is treated as paperwork for after the building is done. Its requirements are scattered through the contract, the specifications and the permits, and most depend on someone outside your team: a supplier's warranty letter, an inspector's date, the owner's staff for training. Left to the last week, each small dependency becomes a delay, and money stays unpaid for months.

Plan back from handover

  1. Build one closeout list from the contract, the specifications and the permits: documents, inspections, tests, training, spare parts, keys and payment conditions.
  2. Give every line one owner and a due date, working back from handover; ask trades for documents two weeks before you need them.
  3. Book the outside dates now: authority inspections, fire and life-safety tests, commissioning and the owner's training. Ask each office how much notice it needs.
  4. Chase documents weekly: warranties, test reports, O&M manuals and as-built markups arrive in a steady flow or not at all.
  5. Walk deficiencies by area with the trades and the consultant, and close each area before the cleaners go in.
  6. Assemble the payment package early: the final invoice and every document the contract lists for final payment and holdback release.
  7. Hold a 20-minute closeout meeting each week: what closed, what is late, who is chasing it.

Common mistakes

  • Starting the list in the last week, when every missing document is already late.
  • Leaving training until the owner's staff are already running the building.
  • Letting a trade demobilize before its documents and deficiencies are closed.

Checklist

Four weeks before handover

  • One closeout list from the contract, specifications and permits
  • An owner and a due date on every line
  • Inspections and tests booked
  • Training sessions in the owner's calendar
  • A weekly list of missing documents
  • Deficiency walks planned area by area
  • Payment documents assembled

Check your understanding

A trade asks to leave site a week before handover because its work is "done". What do you check before agreeing?

Show the answer
Check that its deficiencies are closed, its documents are in — warranties, test reports, O&M data and as-built markups — and that no commissioning or training session still needs its people. A crew that has left takes days to bring back, and one missing document can hold up your own final payment.

Sources

  1. Construction Act, R.S.O. 1990, c. C.30 (section 22, holdback)Government of Ontario, e-Laws · Ontario, Canada · accessed